(Construction) - This was the conclusion of the State Council for Acceptance of Construction Works at the meeting of expanded Hai Van road tunnel project phase 2 on November 20, at Danang.
Deputy Minister of Construction Le Quang Hung – Standing Vice Chairman of the Council, Deputy Minister of Transport Le Dinh Tho, Vice Chairman of People's Committee of Thua Thien - Hue province Nguyen Van Phuong co-chaired the meeting.
![]() |
The delegation inspected Hai Van road tunnel project phase 2. |
On the basis of the completion progress of work items, the Investor's Grassroots Acceptance Council organized the acceptance of bidding packages and fully complied with the legal conditions to prepare the Completion Report.
On the basis of opinions at the meeting and representatives of the Council, Standing Vice Chairman Le Quang Hung praised the efforts of investors, construction units, supervisors, and competent management agencies completed the project beyond schedule. The Council basically agreed to the report and approved the traffic flow operation for Hai Van tunnel operation.
By Khanh Phuong