Fukushima No.1 nuclear power plant completion in around 30 years

22:21 | 22/02/2020

(Construction) - Decommissioning works are underway at Tokyo Electric Power Company’s Fukushima No.1 Nuclear Power Plant as nearly nine years have passed since the Great East Japan Earthquake wrecked the area. The company is cleaning up rubble on the reactor buildings in preparation for removing spent fuel debris while treating the contaminated water.

Japanese government announced the revised time line of the decommissioning works in December 2019 which was the first revision since September 2017. As it maintains the targeted completion period of 30-40 years, the debris removal at No.1-6 Reactors is scheduled to be finished in 2031 and construction of reactor covers in around 2023. Works are to begin at No.1 Reactor in 2027-28 and at No.2 in 2024-26. As No.5 and 6 Reactors did not suffer from severe damages and the spent fuel removal at No.4 has been completed, the company is implementing the works at No.1-3 in a full swing.  

The Green Area where workers allowed to wear regular uniforms increased to 96% of the whole area. In some part, masks or gloves are not necessary anymore. However, the highly radioactive areas still remain. The outside workers wear protective vests made of tungsten.

Beside the reactor buildings No.1 and 2, a 120-meter exhaust tower has been dismantled since August 2019. A crane with an attachment remotely controlled 250 meters away from the site is being used to avoid radiation exposure to workers. (2020/02/12)

The Daily Engineering and Construction News of Japan

Theo

Cùng chuyên mục
  • construction industry supports delay of tokyo olympic until summer 2021

    (Construction) - The Tokyo Olympic and Paralympic Games are to be postponed for about a year due to the corona virus pandemic. The delay is disappointing for the construction industry which contributed to the successful completion of the athletic facilities in time for the event. Though many support the inevitable decision, the industry fears the spread of the disease would have a great impact on the economy and the market in the future.

  • viet nam presents gifts to laos cambodia in fighting covid 19

    (Construction) - In the spirit of sharing difficulty with neighbor countries to fight the COVID-19 pandemic, Deputy Minister of Foreign Affairs Nguyễn Quốc Dũng on Friday handed over medical equipment as gifts from the Vietnamese Government and people to Laos and Cambodian partners.

  • minister pham hong ha attended governments regular meeting online

    (Construction) - On April 1, 2020, Minister Pham Hong Ha and leaders of some units of the Ministry of Construction attended the online Government's regular meeting chaired by Prime Minister Nguyen Xuan Phuc.

  • ministry of construction continues to instruct measures for covid 19

    (Constructing) - The Ministry of Construction continued to have Directive No. 02/CT-BXD on the implementation of urgent measures to prevent and control Covid-19 epidemics.

  • join forces to fight covid 19

    (Construction) - Prime Minister Nguyen Xuan Phuc in the launching ceremony of the whole country to support the prevention and control of the Covid-19 epidemic affirmed: The meaningful jobs are not decided by age, income, qualifications or position. It's all from the heart.

  • sa pa urban development becomes national tourist area

    (Construction) - On March 27, the Ministry of Construction held a conference to appraise the general planning of Sa Pa national tourist are, Lao Cai province, till 2030. Deputy Minister of Construction Nguyen Tuong Van chaired the event.

Xem thêm
  • construction of ropeway begins in minato mirai yokohama

    (Construction) - Osaka-based amusement park developer Senyo Kogyo broke ground to construct aerial gondola transportation system in Minato Mirai, Yokohama. It is designed by Yamashita Sekkei while offshore works are undertaken by Toa Corporation and station buildings by P.S. Mitsubishi Construction.

    09:50 | 27/03/2020
  • more than 100 hotels and resorts registered as isolation points

    (Construction) - According to Savills, due to the impact of the COVID-19 epidemic, as of March 21, 145 hotel and resort projects in Vietnam have voluntarily registered to become isolation sites.

    17:29 | 26/03/2020
  • ministry of construction met online to direct implementation of lao national assembly project

    (Construction) - In the context of an acute respiratory disease caused by Corona virus, on the afternoon of March 20 at the Ministry of Construction, Deputy Minister Le Quang Hung chaired an online meeting on progress of building Lao National Assembly House with Project Management Board, 11th Army General Contractor (Ministry of Defense), Institute of Construction Science and Technology.

    19:43 | 25/03/2020
  • awarding medal to second secretary of embassy of japan

    (Construction) - On March 20, at the Ministry of Construction, there was a medal awarding ceremony for Construction Career to Mr. Takuya Kudo - Second Secretary, Embassy of Japan in Vietnam.

    15:44 | 23/03/2020
  • ministry of construction joins hands to combat covid 19

    (Construction) - Joining hands with the whole country in the prevention and control of the Covid-19 epidemic, the Ministry of Construction has given meaningful gifts to the headquarter of the Vietnam Fatherland Front, the Hospital of Construction, Central Tropical Hospital 2 (Dong Anh, Hanoi) and Office of Ministry of Construction.

    07:54 | 21/03/2020
  • investement of housing projects in can tho

    (Construction) - Cần Thơ housing market will develop fast growth this year. The market would continue to grow due to the Government’s investment in transport infrastructure.

    22:05 | 19/03/2020
  • japanese taisei wins contract of airport terminal building in sri lanka

    (Construction) - Japanese construction company Taisei Corp. Announced on March 16 that it has won a contract to build a terminal building of Bandaranaike International Airport in Sri Lanka. The contract worth 62 billion yen was signed on March 12.

    22:52 | 18/03/2020
  • new station on jr yamanote in tokyo

    (Construction) - East Japan Railway completed the news station in Minato-ku, Tokyo called “Takanawa Gateway Station”on JR Yamanote Line and Keihin Tohoku Line. The station building is made of 630,000 m3 domestic produced timber on pillars and walls along with the steel frame. The building is characterized by its traditional Japanese features such as the origami-like roof of white membranes. The heat reflecting membranes can bring natural lights and reduce energy consumption for the lighting.

    09:11 | 18/03/2020
  • real estate market in difficulty

    (Construction) - The COVID-19 epidemic also had significant impacts on the real estate market, especially resort property and industrial property.

    12:39 | 17/03/2020
  • mayor of melbourne received extraordinary plenipotentiary ambassador of vietnam in australia

    (Construction) - On 12 March, Ms. Lord Mayor Sally Capp - Mayor of Melbourne officially welcomed and worked with Mr. Ngo Huong Nam - Extraordinary Plenipotentiary Ambassador of Vietnam in Australia with representatives of Vietnamese businesses on opportunities of cooperation in the fields of economy, culture, tourism and experience exchange between the two sides.

    21:33 | 15/03/2020
...

Tin bài cuối cùng

Không còn dữ liệu để load